Projects

2 Well Pad

This Dual Well Pad project was completed for one of our valued clients. In addition to the two wells, there was a group and test header that tied into the existing facility. Crews set up a gas lift that is metered in the utilidor heated enclosure. We built stairs across the pipe rack for the well operators to have easy access to the RTU panel. Steps were also created for easy operation of the ESD valves on each well. A very well executed job from the shop to the field crews made for another happy client. 

1000m of 6″ Pipeline

On this project, we worked with the lease owners ground conditions and terms, with our tight workspace and the wet ground conditions, the pipeline crew did an incredible job getting the 6″underground pipeline installed in a timely manner. Crews had one bore section across the road into the new lease where they were tying into a new facility. Weld repair rate was 0% and the bore section went excellent. When the project was complete the lease owners were very happy with our reclamation on the ground conditions and installation of their new fence.

6″ Coated Piping

Internally coated 6’’ STD Produced Water Line Replacement

 

As the prime contractor for the replacement of the defective 6’’ produced water line Complete Projects managed the entire project.

 

Complete Projects pipefitter pre-measured existing piping and remodeled pipe route and flange brakes to accommodate for the coated piping process. Complete Projects taking on all costs associated with the project, materials purchase, scaffold, 40-ton crane, pipe insulation, fabrication, hydrotest, X-ray, painting, coating, installation of piping, quality control and management for the whole project.

 

Planned shutdown, removed old defective piping, and installed 424 FT of piping, 29 spools in total with a 1-day shutdown.

 

Complete Projects QC/QA data management with turnover manual and sign off was completed 

7 Well Multi Pad

Facility Project, Newly installed piping and buildings

The 7 Wellhead centers were measured with Casing Flange angles onsite and building dimensions confirmed at the storage yard. Complete Projects talented Pipefitter designed the pile layout, created the isometric design of piping and fabrication cut sheets. The piping was prefabricated and tested at our Whitecourt fabrication facility.


Onsite, the Pipefitter completed the site pile layout for buildings and supports. Complete Projects installed pilings using our Excavator and pile vibration installation. Crew cut piles to elevation, welded pile caps, welded supports, and set buildings. Prefabricated and tested piping was installed. Dual 8’’ sales outlet lines were used to ship sales gas to two separate facilities using dual 8’’ on lease risers. The lease was open-cut to install a dual 8’’ pipeline across lease set with four risers. 


The project used hybrid SEP’s with no internal tanks. Tank piles and containment were installed, adding two 400bbl tanks and an external 100bbl meth tank with truck out. Wellhead Inlet Highline was 2’’ casing tied to 3’’ tubing line from Wellhead to Sep Inlet. With Rathole covers prefabricated and installed. On lease riser to riser hydrostatic test. Projects 4200’’ of welding prefabricated and installed onsite.

6’’ 6.8km Pipeline

Pipeline laying next to open excavation

6’’ 6.8km Pipeline with two future tie points using Camelback risers. The projects encountered many different soil types, rock protections were needed. 

 

This project had three hotlines, two road crossings and one creek crossing. Weather conditions were on our side for this project and 0% weld repair rate.

6’’ Y lateral Removal

Complete Projects pre-tested line pipe at our Whitecourt facility. Crews excavated underground Y lateral, removed and installed new piping using mud plug procedures welding and supported new piping. 

 

Crew pigged suspended line using our chemical batching process. Complete with blind flange, tagging system, denzo tape and backfilled piping.