Projects

6″ Coated Piping

Internally coated 6’’ STD Produced Water Line Replacement

 

As the prime contractor for the replacement of the defective 6’’ produced water line Complete Projects managed the entire project.

 

Complete Projects pipefitter pre-measured existing piping and remodeled pipe route and flange brakes to accommodate for the coated piping process. Complete Projects taking on all costs associated with the project, materials purchase, scaffold, 40-ton crane, pipe insulation, fabrication, hydrotest, X-ray, painting, coating, installation of piping, quality control and management for the whole project.

 

Planned shutdown, removed old defective piping, and installed 424 FT of piping, 29 spools in total with a 1-day shutdown.

 

Complete Projects QC/QA data management with turnover manual and sign off was completed 

7 Well Multi Pad

Facility Project, Newly installed piping and buildings

The 7 Wellhead centers were measured with Casing Flange angles onsite and building dimensions confirmed at the storage yard. Complete Projects talented Pipefitter designed the pile layout, created the isometric design of piping and fabrication cut sheets. The piping was prefabricated and tested at our Whitecourt fabrication facility.


Onsite, the Pipefitter completed the site pile layout for buildings and supports. Complete Projects installed pilings using our Excavator and pile vibration installation. Crew cut piles to elevation, welded pile caps, welded supports, and set buildings. Prefabricated and tested piping was installed. Dual 8’’ sales outlet lines were used to ship sales gas to two separate facilities using dual 8’’ on lease risers. The lease was open-cut to install a dual 8’’ pipeline across lease set with four risers. 


The project used hybrid SEP’s with no internal tanks. Tank piles and containment were installed, adding two 400bbl tanks and an external 100bbl meth tank with truck out. Wellhead Inlet Highline was 2’’ casing tied to 3’’ tubing line from Wellhead to Sep Inlet. With Rathole covers prefabricated and installed. On lease riser to riser hydrostatic test. Projects 4200’’ of welding prefabricated and installed onsite.

6’’ 6.8km Pipeline

Pipeline laying next to open excavation

6’’ 6.8km Pipeline with two future tie points using Camelback risers. The projects encountered many different soil types, rock protections were needed. 

 

This project had three hotlines, two road crossings and one creek crossing. Weather conditions were on our side for this project and 0% weld repair rate.