This 1800 meter 4” pipeline was
completed for a new, respected client of ours. The project consisted of two
creek crossings, 300 meters of hydraulic jack hammering, and one bore across a
creek. The Complete Projects crews did a great job with the execution of this
project. Our dozer operators cleaned up on the ROW and the excavator operators dug
the ditch in preparation for lowering in the 4” pipeline. The rock hammering on
this project added a challenge to the completion of the job. The weld rate on
this project was 0%. This one-month project utilized 15+ crew members and a
variety of heavy equipment including excavators, dozers, and side-booms.
Operations insured this project was executed seamlessly to meet the projects
deadline.
Complete Projects crews completed a 4 km 4” 4.8